PMP Exam Sample Question
You want to recognize the contributions of some of the
high-performing team members so far in the project.
Which of the following do you need
to guide you through this process?
A. Organizational process assets
B. Stakeholder register
C. Project team assignments
D. Quality
metrics
HINT: Which of the following is an input to the Manage Team process and specifies policies for certificates of appreciations, and other company's perks?