You planned for Contingency Reserves for your office building construction project and used contingency plans to control risks. However, your attempts to control project risks were not effective. What is the next step you should take?
A.) Use a Fallback Plan. B.) Escalate to the project team. C.) Perform the Plan Risk Responses process again. D.) Escalate to the sponsor.
Hint: If the primary risk response plan fails, there should be one more plan to use as a reaction to a risk.