To calculate the total project cost, you use a technique that uses input values selected at random from probability distribution of possible cost. Which of the following options best describes this method?
A) Automated Schedule Development B) Monte Carlo Analysis C) Schedule Risk Analysis D) e-Pert
Hint: This is a simulation technique.