Mary is managing a data migration project. The project is in execution. The project's current total Earned Value (EV) is $25,000 and the current Schedule Variance (SV) is $5,000.
What is the project's current Schedule Performance Index (SPI)?
A) 1 B) 1.25 C) 0.83 D) 0.2
Hint: You need 2 formulas to calculate the correct result.