This PMP exam sample question is taken from
Free PMP Exam Simulator. Go ahead and answer this question. Do you think you will get it right?
You are currently involved in the pre-sales of a telecommunications project. You are an employee of a telecommunications equipment vendor company that also
provides telecom site selection, construction, equipment installation, site integration, and post-implementation support services. Your customer is negotiating a very aggressive project deadline. However, you know that the equipment ordering needs to be done at least a couple of months in advance. This means that you need to place the equipment order at least a couple of months before your planned project roll out. This dependency is an example of which of the following?
A) Preferred
Logic
B) Preferential Logic
C) Hard Logic
D) Soft Logic
Hint: The scenario refers to a dependency that is inherent in the nature of the work.