You are managing a construction project. You have just finished a project deliverable and you are now planning to have your customer and your sponsor inspect the deliverable for acceptance.
Which
PMBOK Guide process facilitates this activity?
A. Validate Scope
B. Control Scope
C. Perform
Quality Assurance
D. Perform Quality Control
Hint: You have completed the deliverable and are now seeking its approval from the customer and project sponsor.