You are managing a website development project and have just calculated your project performance measurements. Your project CPI is 0.9 while your project SPI is 1.1.
Which of the following statements is correct regarding your project's current situation?
A. You are over budget and ahead of schedule
B. You are under budget and behind schedule
C. You are over budget and behind schedule
D. You are under
budget and ahead of schedule
Hint: SPI=EV/PV while CPI=EV/AC.