You are managing a hotel construction project. You are doing great in terms of the project schedule but you have a gut feeling that you might be over budget. You ask your project team to calculate the current project performance measurements. Your project TCPI based on BAC is 0.9.
Which of the following is true regarding your project's current situation reflected by this TCPI value?
A. You are within your
budget
B. You are over budget
C. You are behind schedule
D. You are ahead of schedule
Hint: TCPI is not a schedule performance measurement.