You are a project manager in a strong matrix organization. A team member on the project is consistently delivering her work packages late and below the required quality standards. The issue has been discussed with her several times already but no improvement has been visible. As the project manager you decide that it is time to employ coercive power. What measure will you implement?
A. You
punish her by removing the privilege to work from home for two days per week
B. You bargain with her to give her better assignments if she performs
C. You discuss the situation with her line manager
D. You ask the Human Resources Department to step in
HINT: It's time for corrective action!